plz answer the questions, How do you check the quality of
foundation? and What is the key performance area in quantity
survey?
Answer Posted / dinesh.rk
1>as you know the quality (strength)of foundation is assed
by testing that cube specimen and by quality control during
casting the foundation/
2> there is no such a particular area.. what we need is THE
ACCURACY SHOULD BE 100 % IN EACH AND EVERY ITEMS OF WORK/
| Is This Answer Correct ? | 7 Yes | 1 No |
Post New Answer View All Answers
What is the difference between EPC,DBOOT and BOOT.
Under what circumstances should pot bearings be used instead of elastomeric bearings?
Calculation of curtain wall of box culvert
Explain what is structural frames or systems?
what is stressing
why the cracks occurs in NP3 class Hume Pipe ? And what is bearing capacity of it?
can i get hindi version of is codes based on civil engineering?
What is the frequency of sampling for the materials of cement,Fine aggregate, Coarse aggregate .and refer which code
If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.
A rock anchor 3 1/2” in diameter is placed in rock. The which has an allowable shear strength of 1200 psi. Determine the required anchorage length to safely carry a 80 ton load using a 2.0:1 F.S
1. HOW MUCH CEMENT AND SAND REQUIRED TO PLASTER 100 SQM WALL. 2. HOW MUCH CEMENT AND SAND REQUIRED FOR SCREED WORK OF AREA 30 SQM
What are the points to be considered for calculating cement reconciliation. a)Do we need to deduct the wt of cement bags b)Do we need to adjust the qty due to wt loss during transportation, loading unloading etc or else each bag can be considered as 50 kg bag c)What is the proportion of mix cover block making.
que.is ideal size of bricnk use in india,joint size of mortar in massinary ,how many bricks used in 1cum.how to test at site.what is the possition of marka used in bricks?
Suppose you planning to paint newly fabricated workshop building made of structural steel of 10 tons total mass. How many litters paint primer for 1 coat and 2 coat of top coat?
What is meant by autocad?