hello dear
i have faced problem in drum level transmitter.
the problem is when i engrize the meter meter shows 100%
but the actual level 40 or something plz suggest me
Answer Posted / yomama
The impulse tubes must be filled with process fluid or fill
fluid such as glycol. Additionally the specific gravity of
the fill fluid must be calculated in reference to the
process fluid being measured
Glycerin (Specific Gravity=1.26) for the impulse tubes a
correction must be made.
DP span of 100”= physical height difference of impulse tubes
on vessel
SG of fluid being measured (Oil = 0.68)
Glycerin filled tubes (SG = 1.26)
Since the Low Pressure Leg will be filled with Glycerin we
multiply the span by the SG of the Fill Fluid
100” x 1.26 = 126” so the Lower Range value will be -126”
Span will be the LRV – (SG of fluid) x ( tank Level span) = 68”
-126” + 68” = -58”
-126 LRV
-58 URV
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
1)How many tpes of vibration probe and how many tpyes of vibration. 2)how we can calibrate a vibration probe with tk3 3)what is RMS value in vibration measuring application and how we calculate it.
How process line mpm calculation is done?
what is controlling card in dcs? how u measure dcs memory?what is bus in dcs?how u know dcs speed n ehternet speed?
What is the use of GMV in turbine?
Why is the orifice tab provided?
What is difference between ESD and PLC please Explain me clearly.
whatis range of marcury filled tempereture gague
what is the importance of CV in the control valves? how it is calculated?
What is wet leg condition and why is it used?
which type of filter gives the constant phase characteristics?
Name different parts of a pressure gauge.
how will you check torque value during Factory acceptance Test for control valve/ESD ON/OFF VALE how will you confirm this torque value is being correct, Which document will you be refer.
how many types of spped sensors n vibration sensors?their basic principle n connection?
what effects a surging can produce in the compressor
Instrument QA/Qc what is the project quality plan?conduit inspection RFI. which documents attache with package?