What is D check in a Diesel generator for 1000kva DG
Answer Posted / s.rajeshkumar
gnerally DG requires servicing like B-Check, C-check and D-
check.after 300 running hrs/ one month b check will be
done, in this they will clean all the filters and change
the oil just like bike servicing. in c-check(after
1500hrs), they change gaskit of chambers. in D-check(after
6000hrs, they will check b+C checks, and they will check
cylinders and injection ckts
| Is This Answer Correct ? | 14 Yes | 5 No |
Post New Answer View All Answers
WHY CBCT USE ONLY IN Y PHASE NOT OTHER PHASES
explain the functions of main isolation switches
What is the Designing & Selection Procedure for a DG/Transormer of rated capacity?
What is the difference between PS & metering CT (5p20,0.5 etc.)? Why in PS class CT only Vk is given ? Is PS class CT is more accurate than metering CT?
How generating electric power export to grid from the generating station ?
anyone please send transformer parameter design formulas & details of tap changer ? plz i have interview this week its more helpful for me ?
If any cable burnt how can we identify it burnt by high current of high voltage?
What determines the thickness of the lamination or stamping?
if we have 320KVA Genset kindly advice how much load we can put it.
how you will decide the distance between the power transformer and its fencing
please explain to me how to calculate current,voltage,resistance with formula??
State ohm’s law?
what is different between phase and netural
how external lighting design? please give examples?
what is meant by residual over voltage & residual earth fault ?