what is steel consumption for high rise building column,
beam, slab,footing
Answer Posted / s.k.roy
Based on experience the Consuption for a Building of 10-15
Storey :
Beams 125-140 Kg per cu.m of Concrete
Slabs 80-100 Kg per cu.m of Concrete
Columns 350-400 kg per cu.m of concrete
Footings100-125 Kg per cu.m
In general for a Eartquake Resistant Str in Zone 3/4 the
steel consumption can vary between 6.5 to 7.5 Kg per
sq.feet of Constructed area
| Is This Answer Correct ? | 29 Yes | 7 No |
Post New Answer View All Answers
qty. of cement & sand required (100sq.mtr) for fixing of floor and wall tiles also fixing of marble stone on the floor
Dear Sir, I work in hydro project. I want to hire Scorpio/ Bolero on monthly basis. But how can i justified its amount (Hourly basic). Please solve my problem
by which materials we can prepare circular shuttering with tentative cost of material(rate analysis)
what is difference between NP2 NP3 NP4 CONCRETE HUME PIPES USED AT SITE
Reinforcement details at hinged joint
Use of coping on terrace wall and in 4" wall is compulsory or not ?
What do you mean by the word 'shear'?
what is Short bored pile foundation.
what is pouring and explain
what isload waring calculation
What is the quantity of cement in mix m20 concrete?
What is meant by a context menu in a cad software?
What is difference between code and standard and specification?
How will you Engage Labours on Site?
can any one tell me in detail footing estimation .. i am new here in dubai so facing lots of problem...