On which side, taps are provided in tap changing
transformers and why?
Answer Posted / dilawar husain
The reasons given in above answers are correct. But there
is one more important reason and that is current. On Lv
side the current being more it needs heaviour contacts as
compared to HV side where the current is far less and
easier to handle. Also in case of ON LOAD Tap changers the
current is divirted to a bypass circuit for the duration
the tap is changing the pposition. This bypass circuit is
easier to design for lesser current on High voltage side.
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
The 3 phase 400 hp 440 volt slip ring induction motor do not take one phase amps why ? The motor is running good condition
A 100 kVA , 400 v/250 kv testing transformer has 8% leakage reactance and resistance on 100 KVA base . A cable has to be tested at 500 kv using the above transformer as a resonant transformer at 50 hz . if the charging current of the cable at 500 kv is 0.4 A find the series inductance required . Assume 2% resistance for the inductor to be used and the connecting leads . Neglect dielectric loss of hte cable . what will be the input voltage to the transformer ?
What is the diff. between single compression and double compression gland
how to find impedance , mutual indatnce in transmission lines
HOW DOES THE ELECTRONIC ENERGY METER WORKS?
state the working of discharge lamp?
Briefly describe means used by electricity suppliers to influence the flow of active and reactive power in power networks (one for each type)?
State and define norton’s theorem?
what happens to the water pump if ground water level is slowly decreasing?our water pump is varying from no-load full-load due to this problem
i am completed diploma in ece,and working in ht and lt lines.so is elligible diploma in ece for get electrical C Licence?plse give ur opinion?
Sir, My doubt on cable sizing calculation, Load:74 KW calculated cable 1 run 50mm2. Now client asking us to reduce cable size by increasing runs. Sir, My question now when my mind strikes with 2 options 1) Divide load 74/2 = 36 and calculate cable for 36+36 making it 2 runs or 2) Simply i can divide 50mm2 /2 ie. 2 runs of 25mm2 Please suggest me sir
how mass curve differs from hydrograph.
WHAT IS THE FORMULA FOR CALCULATING CURRENT RATING(DIRECT IN GROUND OR AIR) OF ARMOURED(XLPE) CABLE OF 4C,16Sqmm?
at what rate the micro controller increment its timer....is it 1micro seconds or 1/(12*10^6) seconds
excitation limit of an excitor