what is periode of deshuttering of slab our span length
21m,and width 2.5m grade of concrete M-35
Answer Posted / raju msra
14 days
| Is This Answer Correct ? | 10 Yes | 1 No |
Post New Answer View All Answers
Dear Sir I Mahesh C. Bhamre have already given a Exam for Superintendent Officer / Public relation Officer Exam Dharmday Aaukta held at Nashik on Date 29/08/2010. My seat no was 5040247. and my cell no is 9822677994. and my mail Id is - mahesh.bhamre@rediffmail.com So can you pl send me details of result of respective exams. Thanking you in Anticipation.
Stringer How many cm goes to landind
Need help in designing a degasser tower for 2m3/hr DM plant, also send me the formulae used
que.is ideal size of bricnk use in india,joint size of mortar in massinary ,how many bricks used in 1cum.how to test at site.what is the possition of marka used in bricks?
what is diffrence between catchment area,watershed and basin?
Required amount of Steel bars, cement/ square feet for roofing of residential building upto 3rd floor.
What is the difference between a wood shake and wood shingles?
What are the common ways of demolition?
Dear sir, i want to NBCC & NTPC previous exam papers email Id : madhu_bingi@yahoo.co.in
does a b.tech civil engineer fresher supposed to know how to design rcc structure?
sir, whitch is the best book (writer name) for prepration of gate....
how many sqft or cft of work done by a mason per day in all works such as brick,block,concrete,shuttering carpenter,reinforcement fabricator,painter,door window carpenter.....everything thank you
for Precast foundation howmany days required we can shift the foundation with american Standards i need reference with section any body can help
Design a cantilever type retaining wall to retain sand for 4m above the ground. The sand fall slopes at the rate of 1 vertical to 2 horizontal. The weight of sand is 18000 N/m3, the angle of repose being 30. The safe bearing capacity of the soil is 200 kn/m2 at 1/25m below the ground level. Use m 15 concrete mix.
Why is the use of granular sub-base in concrete carriageways not preferred, explain?