how do we calculate wastage of steel in the site,what r the
items to taken into account for wastage calculation?
Answer Posted / pr
Wastage= Actual consumed-Theoretical consumption
% Wastage=(Actual consumed-Theoretical
consumption)x100/Actual consumed
Actual Consumed= Total issue- (Stock at site+ Scrap)
Total Issue = (Total qty Received from Market+received from
other sites-Total qty dispatched to other sites)(+/-)rolling
margin
| Is This Answer Correct ? | 18 Yes | 2 No |
Post New Answer View All Answers
What is alternate bid?
what could be the production cost of 1 cum of concrete by CP30 plant
which steel is better for residential building tmt steel or hysd steel
cud any one send me tech quest paper(civil engg) at tarizus@yahoo.com
What is difference between combin footing & rapt footing
What is GSB gradation
How to make a c++ program that converts any base to base 10?
what is conrete grade ,how are depent on concrete grad and size of concrete?
What are new methods /technologies of pothole patching?
Define What glue is least sticky?
what is the steel difference between np-2 and np-3 pipes and weight also
which are the Indian auther books for STONE COLUMN/GRANULAR PILES?
suppose we have a tendency to make a hole on the surface of the simple supported beam, than where we goes to make it?
What is the veriplus for ellips card length formula (major axis 3.4m,minar axis 2.6m spacing 0.2m
what is the difference between tsp & tower