we are small scale industry in production of rice & rice
bran. Pls let me know how to take contract demand for our
industry.. (for information we have total 600.hp)

Answer Posted / sumeet

First of all please estimate your mill load, office load
(lighting load and air conditioner load).
As per you have shown 600 hp load your contract demand will
be 447.6 kW i.e 527 KVA considering 0.85 power factor

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

how to setting voltage RTCC panel

1219


how we can calculate power factor in single phase & three phase ?thank u

1563


what is the use of commutator in dc motor if we supply ac ? commutator is used to convert ac to dc.and it is used to arrange the flux in unidirectional in case of dc supply. if we give ac as supply to dc motor what is the use of commutator?

1649


how can we make cable shedule for controll wiring ? which details must be required for it.?

1649


Explain few advantages of electric traction system?

596






What would cause a 240v choke that should give 110v out on a 16w lamp to gradually increase to 160v?

1754


What is the Minimum winding resistance of motors ( small & big)? referance range

1853


any one can explain what is the size of pvc,armoured, various sizes of powr cable dia?

1455


Explain the operation of grid connected central solar inverter ?

1035


what is capacitor voltage transformer?? how it is different from potential transformer?

1701


please send me previose rrb junior engineer qustion papers

1641


What is the accepted limit to increase the choosen transformer capacity over the load and why ?

2711


how to remover corona effect and hysteresis losses from contactor

1570


If one lamp connects between two phases it will glow or not?

620


what is model question rrb junior engineer electrical gr.II

1554