I've one slab of 24m x 43m. How to calculate required steel
For this slab.

Answer Posted / surajit ghosh

LBD= 24 X 43 X 0.125 (SAY, REQUIRED TO ACHIEVE AS PER
DESIGN)= 129 CUM
VOLUME OF STEEL 1% (SAY, REQUIRED TO ACHIEVE AS PER DESIGN
& BBS)= 1.29 CUM= 1.29X 7850 kG= 10126 kG, Apx= 10 Ton.

Is This Answer Correct ?    14 Yes 6 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Which code specifies the specification ofthe construction joints to be provided in the raft slab of a basement which is 6 m deep.what should bethe detail of such a joint?

2042


what is civil enginnering & what you need of this course?

1799


What is Critical path in Ms-Project ?

701


What is the wall thickness of NP-3&NP-4 hume pipe as per I.S code

1620


How to calculate material and labor required for 100 m2 plaster?

1252






Explain what are the skills required to become an architect?

705


What should be the standard roof height like to be?

675


what should be the PCC ratio to construct a plinth of (40x40x4)ft...??also its estimated cost??

2640


as per is code, what is the minimum content of opc and ppc cement for rcc structure

1746


How to calculate plastering for elevated water storage tank

825


What is the amount of work done by a carpenter, bar Bender and plaster Mason in interior and exterior plaster

1852


WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.

1581


pls give me some basic informations in construction of a structure?

1614


how i can calculate the actual nos & size of steel to make 1000sqft. x 3"thick slab

2011


What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)

1676