Cube tests of concrete are failed at 7 days and 28
days.What is your next action?
Answer Posted / vaibhav jadhav
Any is code not give the clause regarding demolishing of
structure if cube fails in 28 days. but IS 456 & 516 give
the clause if strength of cube is less than FCK then
proceed for NDT Test i.e Rebound hammer if fail then go for
Ultrasonic test after all the NDT fail then proceed for
Core cutter also if U found result less then FCK then go
for Retrofitting with suggestion of consultant.
| Is This Answer Correct ? | 33 Yes | 2 No |
Post New Answer View All Answers
WHAT GOAL DO YOU HAVE IN YOUR CARRIER?
i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?
Forces in a Shear Wall are in plane or out of plane ?
i need the syllabus for the direcr recruitement of executive engineers in andhrapradesh
What is the Systematic Responsibility Site Engineer? Who are the above and under co-oridinating ? What is office & Site co-ordination of Site Engineer?
I have an span length 16 ft c/c
what is the cost of rcc roof casting of 400 sq. ft. in kolkata
Design an underground tank of internal dimensions 6m x 3m x 3m. The soil surrounding the tank always remains dry. The tank shall be provided with a roof slab. The soil weighs 16000 N/m3 having an angle of repose of 30.
how gradation of aggregates effect on slump of fresh concrete?
What is the density of most of construction materials?
writte a c prog. to acept 5 no. from consule and then display them back on consulte in ascending order
What quantity of 1.0 m3 bricks required?
What is made from large rocks, which protects the base of cliffs?
how to estimate costing from quantity givin in BOQ and according to this how we fill tender and final rate for perticular work.....?
Why should pumping be not used in case of concreting work?