Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how to calculate 1:2:4 ratio concrete cement, sand, metal
and water please give me brief calculation

Answer Posted / sandeepthakur1981

for 01 cu.m.

cement=1.52/7 =.217
= .217x30= 6.51 bags.

sand= .217x2= 0.434cu.m

aggregate= .217x4= 0.868cu.m

Is This Answer Correct ?    94 Yes 35 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

how to calculate the size of triangular ring in rcc column?

1810


percentage of metal,clay or soil & water in water bond macadam roads to know the quantities for each in total volume of 11500 cubic meters

2150


why do we provide haunches in rcc box or underpasses?

3028


What is Curtailing of R/F

2483


acceptance criteria for concrete works

2207


What will you do if a portion of load bearing wall collapses under your supervision?

2006


do you think we shall remove un wanted soil for foundation excavation even if the thickness of the soil strata is more than 8m ?

1697


very simple or less time consuming formula for reinforcement calculation by moment

1498


What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?

2871


Calculation of Pier Cap with tapper area?

6350


What is binding spacing of the rebars at lapping zones.

1312


Advantage of Aluminum form work in terms of activities can be skip and cost too

1073


pls send me interview question paper with answer of EIL/AAI/UPSC/RPSC because i am doing prepration of compitation exam of UPSC for the Asst. Executive Engineer

3118


wat would be the probable interview questions and GD topics for IOCL exam?

9820


What is the density of 1:1.5 (Cement:sand) ratio in plaster? And Conversion in 12.5 mm thickness per square meter? Howmany Kg of Cement square meter in ratio of 1:1.5?

3356