how much quantity of blocks, cement and sand is required to
complete 1sq.m of CC Hollow blockwork. Size-16"x8"x8". Also
what is the cement sand ration commonly used?

Answer Posted / k.amirthalingam

Quantity of material used for a Hollow block work
(400X200X200)?

1. Qty of HOllow block is 10 to 12 numbers / Sqm
2. Cement sand ratio preferable is 1:4
3. For 1:4 CM the cement, sand calculation as follows

Volume of mortor = Horizontal joints 5 rows of 200 mm wide
20 mm thick = 5*.2*.02 = .02 cum

Volume of verticaljoints : 5*2.5*.2*.2*.02 = .01 cum

Total = .03 + 30 % wastage = 0.039 Cum of Cement Mortor

For 1:4 ratio

Weight of cement in 1 Sqm = .039*1*(1/5)*1440 = 11.232
Kg /Sqm

Volume of Sand = .039*1*(4/5) = .0312 Cum = 1.11 Cubic foot


NOTE: But in actual it occurs more than the above
calculated values because many unskilled people filling the
hollow portions of the block. This is the wrong practice.
The Laying system is such that the hollow portion to be
overlapped with filled portion hence the hollow portion to
be maintained. This will give good heat reduction inside
the building.

For more queris mail me at ameerabic@gmail.com

K.Amirthalingam from Ariyalur

Is This Answer Correct ?    134 Yes 47 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is Joule Brayton Cycle?

780


trapozidal

2020


What is the l/d ratio of cantilever beam?

1482


how to calculate 1:5:8 ratio concrete cement, sand, metal and water please give me brief calculation

1228


WHAT WII BE THE WATER ABSORPTION POWER OF WOOD ?

1787






In block work seawalls what is the purpose of slip joints?

768


what is the service corridor?

1926


What is absolute coordinates?

703


step by step procedure to find out the percentage of steel in coloum,beam,slab,footing in detailed

1922


what is the ingredient value of 40mm and 20mm aggregates?

1557


What is the best type of wood glue?

705


Differentiate first angle & third angle projection?

670


what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?

1673


List out the potential risk factors for workers on the construction site?

652


What should be the standard roof height like to be?

678