9*8m slab 1:2:4 ratio use for M20 mix how much cent is
require it will become in cum but i want bags.
Answer Posted / binubal123
Volume of Conc needed=9*8*0.01(assume)
=7.2Cum
M20 mix (1:2:4)
material
cement by vol=7.2*1/(1+2+4)
=1.028
Sand By Vol=7.2*2*1/(1+2+4){2*1.028}
=2.05
Agg By vol~4*1.028
=4.114
Cement in bag req=1.028*308.53(Cement Constant frm Practical Info for Quantity Surveyor P.T.Joglekar) =317.34Kg=317.34/50=6.36bags
| Is This Answer Correct ? | 1 Yes | 5 No |
Post New Answer View All Answers
if mineral admixture add into concrete then what is the differences between full cement concrete & fly ash added concrete of their SP. Gr.?and for the changes of SP. Gr. what is the changes in concrete
what is difference between NP2 NP3 NP4 CONCRETE HUME PIPES USED AT SITE
i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?
What do you understand by “preset” during the installation process of bridge bearings?
What is the number of IS code of practice to be followed for hydraulic design of sewerage pipe line?
How do you calculate load bearing capacity of a waffle slab?
150mm bricks size how many use 4.14 m3
How many times we can use Fresh bentonite ford wall execution? Would like to know the clear concept of recycling. After flushing can we use it for another time time for flushing? Or we have to use it for for excavation only?
How can we demolish concrete beams?
4. Differentiate between NC and OC soils. Draw curves for (i) Stress vs Strain (ii) Volume charge vs Strain (iii) Pore pressure vs Strain for these soils
What is meaning of tlc
i just want to know how much require sand and cement for 1 sq.mt including wastage. Please guide me as soon as possible.
Pls provide me with the calculation or codes related to de- shuttering of flat slabs
What is the amount of work done by a carpenter, bar Bender and plaster Mason in interior and exterior plaster
what is the max. and mim. height of vertical post in informatry sign board which is used in highway projects.