Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to find quantity of cement mortar?
I want to know the req quantity of cement for plastering 300
sft in final coat with 12 mm. Any math involved? Plz help

Answer Posted / deepak katyal

Area of plaster surface = 300 sq.ft. = 27.868 sq.mt.
Thickness of Plaster = .012 mt.

Volume of Cement Mortar = 27.868x.012 = .334 cu.Mt.

Extra for wet mix (wastage) 20% = .334*20/100 = .0668 cu.mt.
Extra for dry mix 30% = .334*30/100 = .1004 cu.mt.

Total Volume = 0.5012 Cu.mt.

Ratio of Plaster = 1:5
Area of cement = 0.5012/6 = .083 cu.mt.
Weight of cement = .083X1440 = 119 kg
Bags of cement = 119/50 = 2.39 bags.

Area of Sand = .5012*5/6 = .417 cu.mt.

Is This Answer Correct ?    5 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

I want to know how much the lapping length for the pilecap reinforcement.. we r using single pile cap which is 24mby54m and 2.5m depth.. total 91piles are supporting the pile cap.. how to do a steel reinforcement??

2297


How much Tolerance factors like 1. brick work 2.plaster 3.painting 4.floor tiling 5.wall tiling 6.shuttering 7.concreting 8.steel

1794


how clculate excavated or backfilling quantity by simpson's rule

5081


1.Why we are preferring 43 grade cement than 53 grade cement. 2. Approximate cost difference between 43 and 53 grade cement. Thanks.

2669


how to find quantity of concrete in PCC M15

2096


"how can we find the approximate quantity of materials using in a building or total Expenditure in percentage for rough estimate after known the construction area(sqm)".please if you know something about that please post the answer.

2024


What is meaning of Canceled/Flat Beam. What is difference between them? Both type of beam can bear same load if size (width)of the flat beam is increases and depth is same as slab thickness? Kindly suggest to me.

2250


What is the cost of shuttering per Sqm.? How it is calculate by thumb rule...?

1872


how much quantity of 1.5" nails and 2.5" nails are required for conventional formwork shuttering?

1638


What is pre-stressed concrete?

1063


which has high compressive strength between hollow block and brick masonry?

2318


Explain moment of inertia?

1060


sir when can we expect the AEE results and when will be the interviews sheduled please guide us in this regard thanking you

2397


Explain what is the difference between built area and super built up area?

1141


explain the advantages of total stasion

2129