how to rectify the problem ,if we erected the DPT instrument
wrongly of hp on lp side and lp on hp side?
Answer Posted / haridass
1. The easy physical way, turn the dp cell 180 degrees and
connect the fittings and tubings.
2. Check the LRL/URL using HART comm, if the range of the
transmitter is capable mean change the LRV/URV.
| Is This Answer Correct ? | 3 Yes | 1 No |
Post New Answer View All Answers
what is a half wave, full wave, and bridge rectifer.
i have steam drum height 1000mm. and i want to placed the transmitter below the tap.how i calculate.
How to convert mmWc(mili meter water colam) to tph(ton per hour)?
how to measure draft pressure in transmitter pl. give its single line digram
What is the difference between modbus,fieldbus & profibus
in natural gas indirect water bath heater,how to prevent the problem of backfire from firetube during ignition...becoz of this backfire performance of wbh is going low.
in valve is constructed as per SME B 16.34, then which standard is used for fire testing of valve?.
wich is coming the first HAZOP OR SIL
A PLC is programmed to drive three motors A, B and C as follows : After running motor A for an hour, motor B should get ON and motor A should get OFF. And after running motor B for an hour, motor C should get ON and motor B should get OFF. And after running motor C for an hour, motor A should get ON and motor C should get OFF. (That is, a cyclic repetition with time period one hour) Now, the second condition is: If any motor gone faulty and is tripped, the consecutive motor should get ON and the faulty (tripped) motor should be eliminated from cyclic repetition. The remaining two motors should bear the cyclic repetition of one hour each. (For healthy motor take logic as high and for tripped motor take logic as low) Now, the third condition is: When motor A load(Amps) exceeds 60% of its rated load, motor B should get ON in parallel to motor A. And when both motors A & B are running in parallel, and if their load exceeds 60% of their rated load, motor C should also start in parallel to A & B. [Here the cyclic repetition is eliminated, until their loads become normal(40%)] [Take logic high(1) for load at 60% and logic low(0) for load at 40%] Now draw a flow chart or a ladder diagram to fulfill the above condition.
how do calibrate the valves.. with clear manual
flow transmitter formula?
what is 24vdc live and dry supply
What is wet leg condition and why is it used?
With N nodes and B branches what will have a network ???
Can anybody tell me how to select the size of earthing cable for DCS & PLC system.Please tell me any relevant answer here or mail it to me.