what is the specification for silt content in sand
Answer Posted / dharmendra
x is the initial mark , but after adding water and waiting
for 1 hr then we have to take the SAND+SILT = A ml , and
then the only sand level say B ml
silt content = (A-B)/B *100
AND (X-B)/B*100 is BULKING OF SAND
| Is This Answer Correct ? | 39 Yes | 16 No |
Post New Answer View All Answers
indian standard split spoon sampler
how much required strength of cement concrete bricks(size 230x115x75mm)
what is pqc
GIVE US DETAIL OF YOUR PRESENT EMPLOYMENT STATUS?
what isload waring calculation
satart to end steps by step process of building construction...? i want to planning theme accuretly
Floor tile measurement? Wall to wall or skirting to skirting
How to testing voids of filled aggregate in bitumen mix design
it is possiblee to produce concrete with out cracks...
what is the types of surveying?which type of survey carrying for type of work?
How do you calculate load bearing capacity of a waffle slab?
115mm thickness brick work how to required mortar
what is anchorage length,lap length and (dont remember the last one)
In Residential home construct footing,beam, column,lintel,rcc roofs which dia rod used how to self assumed
If we buy crush sand for 3200/ Brass and cement for Rs350 /Bag and flyash 1200 / tonne....and my production is 230 Bricks per bag than how much cost is required for 1 flyash brick?