THIS IS THE EXACT PROCEDURE ALL OF U
GIVEN THICKNESS OF PLASTER = 12MM = 12/1000 M = 0.012M
RATIO (1:6)
SINCE YOU HAVE NOT GIVEN ASSUME THAT 100 SQ.M OF PLASTER IS
DONE.
THUS VOLUME OF PLASTER = 100 X 0.012 =1.2 CUM
ADD 60 % FOR UNEVENESS OF PLASTER SURFACE AND VOIDS
TOTAL VOLUME OF PLASTER WORK = 1.2 + 60/100 X 1.2 =1.92 CUM
VOLUME OF CEMENT = 1.92 / (1+6)=0.274 CUM
NO. OF CEMENT BAGS =0.274/0.0347 =7.89 BAGS (NOTE VOLUME OF
50 KG CEMENT BAG IS - 0.0347 CUM)
VOLUME OF SAND = 0.274 X 6= 1.644 CUM
| Is This Answer Correct ? | 219 Yes | 44 No |
Post New Answer View All Answers
Which is the latest version of solidsworks?
What is the difference between Fe 500, Fe 500 D and Fe 515.
the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum
Which code specifies the specification ofthe construction joints to be provided in the raft slab of a basement which is 6 m deep.what should bethe detail of such a joint?
How many times we can use Fresh bentonite ford wall execution? Would like to know the clear concept of recycling. After flushing can we use it for another time time for flushing? Or we have to use it for for excavation only?
what is castigliano theaorem
If we don't have drawing for Excavation of building,At what rule we will go for excavation and how much depth will go for a villa?
What is the veriplus for ellips card length formula (major axis 3.4m,minar axis 2.6m spacing 0.2m
What ingredients with% found in ppc cement??
is concealed wiring a problem in fly ash brick wall?
Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day
What are the steps involved in the concreting process?
what is anchorage length,lap length and (dont remember the last one)
what is Short bored pile foundation.
How to calculate the weight of sand am 20mm course aggregate in 1 c.m M25 concrete Which use 400 kg of cement ?