1.what to do if ferquency of any power system continue to
decrease ?
Answer Posted / sethar12
The problem is not that the frequency of the generator is
decreasing, but the problem is that when this frequency
decreases upto the underfrequency limit of the turbine (or
generator)(frequency bandwidths as given by manufacturer)
(generally at 48Hz). It must be noted that the turbine (or
generator) can run for some commutative duration in
different frequency bandwidths even below 48Hz, but it is
better to avoid in these bandwidths because turbine blades
may damage due to resonance.
The most effective solution is the load-shedding
(distribution side) (by asking the transmission network
controller).
Otherwise reducing the generator load manually.
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
How many methods use the load flow solution?
Sir pl provide 5 year sample paper for post junior engineer(electrical).I have currently applied for junior engineer (electrical) on RRB Ajmer
sir,in our plant we r using SATEC PM172E power reading meeters in HT panel side it is monitoring the MB data smart viewer(sever).but last one week we did not get readings inthe server only available in meeter.tell me how communicate meter and server. and also what steps we take for checking.
WILL SCHNEIDER MAKE ACB(MASTERPACT)TRIP ON REVERSE POWER?
What is power in wattage of 8.5 TR AC
Please tell me in DETAIL about the following 3 types of fuses or recommend me a good power system protection book or a website link ? 1.Dropout Fuse 2.Striker Fuse 3.Empulsive fuse (not sure if its impulsive or explosion fuse , sorry)
If I want to buy a new Xformer for my plant what are the main parameter will I need to check?
why we used ZNO in Lightning arrester.
Which contains in POLE ASSEMBLY of a 11KV Kirloskar-make SF6 (Model No-FP620A12)? Will u clarify with drawing?
clarify types of motor operated valves and advantages
What are the Formula of computing Back up Time of 500kVA UPS with 4 Battery Banks, each bank composed of 43 pcs of Batteries 12V150Ah. How to compute the Back up Time of UPS? We have also 3X500kVA UPS running in Parallel same composition as I write above.
what is meant by neutral compensation factor and where it is used
How to Calculate Current Rating of SDFU (Switch Disconnector Fuse unit) for Protectionof Capacitor Bank connected to Busbar of 800Amp,in LV side of 11/0.433KV, 250KVA Transformer?
what are the advantages and disadvantages of speed control of 3 phase induction motor by varying frequency explain with drawing
What are the disadvantages of thermal power plant?