What is the ratio of Grades M10,M15,M20,M25,M30,M35,M40.
Answer Posted / brajesh kaurav
ratio of M10-1:3:6
M15-1:2:4
M20-1:1.5:3
that rattio is nominal mix basis.above M20,than mix design
is preford.basically M25 consider is 1:1:2
| Is This Answer Correct ? | 3287 Yes | 307 No |
Post New Answer View All Answers
My daily concrete volume of M25 concrete is 1st day= 25 Cum 2nd Day = 45 Cum 3rd Day = 55 Cum 4th Day = 22 Cum 5th Day =72 Cum 7th Day = 49 Cum. What will be acceptance criteria of concrete considering as per is 456 cl.15 and table 11 (cl 16.1 and 16.3).
Howmuch bend to be provide for 200/600 BEEM
What is the Null Point of chimney in Power Plant
Which are the top apps for you civil engineering?
If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?
why top layer of block work shoud be full size if any cut block adjustable than another layer?
how much st. steel is required for staging of concourse slab of a elevated metro station allowing through traffic .
Tell me about triple point of water.
Gave a cantilever beam with 3 legs.Told to draw the bending moment diagrams, axial force diagrams and shear force diagrams.From BMD he asked to show how the reinforcement will be provided on the tension side.
Design a shear wall of length 4.20 m and thickness of 250mm subjected to the following forces.Assume Fck = 25Mpa and Fy = 415Mpa and the wall is a high wall with central part 3440mm x 250mm and two 380mm x 760mm strong bands at each end with following loading. S.No. Loading Axial force Moment Shear 1 DL+LL 1950 600 20 2 Seismic load 250 4800 700
Bernaullis theorem deals with the law of conservation of mass momentum energy none
does a b.tech civil engineer fresher supposed to know how to design rcc structure?
a solid steel rod length 2m dia and 20mm vertically hangs from celling and has a collar firmly atteched to it. above the collar an annular rubber washer of 40mm th. having stifness k = 5n/mm is placed. determine maximum stress in the rod caused by mass of 5 kg falling through a height of 1.2m.
how to calibrate the RM 800
how to shuttering is used in slab