contract demand is also called billing demand and it is not
likely to be exceeded by the consumer.It is the assured
maximum demand.Max demand is the actually recorded one
during the month and the consumer will be penalized if this
exceeds the CD as per applicable rules formed by the supplier..
| Is This Answer Correct ? | 61 Yes | 9 No |
Post New Answer View All Answers
can we use engine degreaser for electrical motors?
Write the force balance equation of ideal dashpot element.
What is steady state response?
11kV capacitor bank of rating 2.4KVAR, is charged with protective relays of only over current & Earth fault &.......without Over Voltage, Under Voltage & Neutral Displacement Relay. Is it advisable??
What is the Basic Difference bitween Long Shunt Connection and Short Shunt Connection in DC Generator?
In which of the following case, the rotating magnetic field is reversed? A regenerative breaking B plugging C dynamic breaking D forward motoring
Whether the vacuum contactor requires Short circuit protection?If No,why?
How the over load setting for HT Motors calculated-provided in Numerical Relay
We have 5 Distribution sections with variable loads&We have 3 Gensets(500kva,380kva&250kva) our total load is between 400kva to 600kva. so how could we connect 3gensets.
why induction motors are rated at 0.8 power factor.
in electrical control panel. how can i choose the cable rating. (example - 11kw motor, 18-25A mpcb}
For a 6.6kV Motor it is recommended to do megger test with 500 V d.c and not more than 5kV d.c but the Hi voltage withstand test should be performed by 12kV AC. Why the dc voltage test should be limited but AC voltage withstand test could be with such a high voltage?
at work i have a genertor/alternater what is the easyest way to work out if it is dc or ac?
Is there any rule to select the voltage of motor based on KW rating? What is the rating above which lt motor becomes the HT motor?.
volts=230 c=10mf a=??