Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.
Answer Posted / r. ansari
Formula for trapezoidal footing quantity
Q = h/3{(a+b)+√ab}, a&b is area of bottom and top portion
=0.5/3{2x1.7+0.15x0.15+√3.4x0.0225}
=0.583 Cu.m.
| Is This Answer Correct ? | 11 Yes | 10 No |
Post New Answer View All Answers
how to calculate quantity of bricks in circular manhole with examples.
HDPE pipe standard bends using for TSE irrigation? is it possible to use 30 degree?
Pls help me to arrive the rates for centering shuttering for highbay using H-frames?
what is the steel difference between np-2 and np-3 pipes and weight also
In tower foundation, on the time of 3 mtr pit RCC casting if water and mud is their surface of PCC then what will be do?
04. a. Slenderness ratio…………… 1 b. If the height of a stage is 15-0 & dia. of the prop is 5, the slenderness ratio is….… 1 c. If the height of a stage is 10-0 & dia of prop is 3, the number of bracing will be…… 1
How much does it cost for a R.C.C cover slab of size (450mmX 600mmx 100mm) double rf net given in feets using hand mix concrete?
what is Quantity of stone and sand required for one cubic meter of stone work (UCR)
how to calculate the steel in 500yard
what is mail role & relationship between senior Civil engineer to consultants , Construction manager ,project manager, project engineer ,Technical engineer & qa/qc engineer ? what is the responsibilites of Senior Civil Engineer?
What is the difference between chamfer and fillet?
50 acre of land to be reclaimed for an average height of 2.5 mt. Dredging area is 500mx200m size. what is the dredging depth required to reclaim the area?
hi every body..i have applied for RRB section engineers CIVIL.i wanna prepare for that,so can any one suggest me some books and where can i get the syllabus for this..i would be vry greatful if any one can help in this regard
for pretensioning which will yield first and same for post tensioning?
what will happen if one could not properly follow the spacing of slab reinforcement bar?