Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.
Answer Posted / r. ansari
Formula for trapezoidal footing quantity
Q = h/3{(a+b)+√ab}, a&b is area of bottom and top portion
=0.5/3{2x1.7+0.15x0.15+√3.4x0.0225}
=0.583 Cu.m.
Is This Answer Correct ? | 11 Yes | 10 No |
Post New Answer View All Answers
How to calculate the load of partion in flat slab if we use brick?
Prepare a Schedule for a Highrised building from starting stage to Handover?
which has high compressive strength between hollow block and brick masonry?
who to find building iron rod strenth
I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?
Define graphics window?
if the nitrates more than 45mg/l in water lead to disease then what is it called
plz.show development and anchorage length in simple diagram.
Explain how you can turn off the display for dimension in CAD?
Advantage of Aluminum form work in terms of activities can be skip and cost too
What Are The Steps Involved In The Concreting Process, Explain?
how to balance aggregate during mix design of concrete???? how to calculate moisture content like C/A,F/A and how many percentage using ice instead of water for example of we are preparing ice concrete??????
How many bricks are there in 100cft?
1. For 10sq.m area(47 kg bitumen contain) of 45 mm thick bitumen mix layer..how much bitumen is required for 1600 sq.m and how much aggregate need for that ?? 2. And much tonnage of bitumen mix required for 10 sq.m area of 45 mm thick. Please give answer...
what is E