why is the vector group analysis done in transformer tests
Answer Posted / ganesh nayak
Vector anlysis is done to check whether the transformer
under test is suitable for parallel operation with another
transfomer having same vector group and voltage ratio but
difference in KVA rating.And to know the phase displacment
and polarity of the transformer.
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
What is mean by hot and cold loop testing?
what is interpose? where it is used and why it is used?
for 750 kw LT load what will be the ht kva
how to calculate regulation constants for over head lines? and what are the regulation constant for raccoon conductor at different voltage level and different P.F?
What is ideal IR values for ground and neutral.
What happen to the transformer if the OLTC frequently used for lower and raise occured 50times daily?
how to read idmt curva
Define gain margin?
Explain the difference between verilog task and verilog function?
Can anybody post questions asked in Engineers India Limited Interview? Thanks in advance.
What is Instantaneous Earth fault relay,how will work
Differentiate between kirchhoff’s first law and kirchhoff’s second law?
Two liquids hot and cold in two vessels are there and an metal bar acts as a conductor of heat between the two vessels. what happens then. what happens after 24 hrs?
WHAT CAUSED THRESHOLD VOLTAGE TO EXIST?
How Can I calculate for the photometrics requirements for a street lighting? Data given are: 45 units of 6 meter light pole with 150 watts metal halide lamp, 220 volts and installed in a promenade area.