If 11 KV breaker on the primary side of a 11 KV/3.3 KV 12.5
MVA transformer can be installed at a distance of 1000 mtrs
through a 11 KV cable. If no what are the probable reasons.
Answer Posted / bala_vlsi
1000 m is not possible because the voltage drop will be
very high so you will consider lot of cable and it is not
practical . if want this system you should consider
overhead line method
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What are the different sign conventions used in electric circuits?
which one is more efficient, torq, power & ecnomy with the same frame size AC motor / DC motor?
how can we save enegry by using VFD for Resiprocating Air compressor which is having more unloading running hours
HOW TO CALCULATE THE HEAT AND LOAD OF LT-SUBSTATION WHICH CONTAINS 2*1MVA TRANSFORMERS,LT-SWITCH BOARD,MLDB,ACB,BUSBAR,ETC,......?
Why do we use copper cable for HT Supply and why not Aluminium?
How to perform a DC resistance test In Alternator and their proceduces?
A generating system will have a total capacity of 300 MW. Find the probable forced outage when the capacity is supplied by two 150 MW units. The operating probability of all units is P=0.98 and forced outage probability rate Q =0.02 .
What is the most accurate way of testing ELCB?ELCB is better than RCD?
What is a signal flow graph?
WHat is the requirement of installing FAST ACTING EARTH SWITCH in GIS and how is that integrated with protection system. How and when does it operate?
what is the safty of poly phase tranformer?
Why CBCT rating is 50/1A
Define what is power quality meter ?
why do we have spikes enough to burn electronic boards, when generators are not grounded
can we use engine degreaser for electrical motors?