I'm puting roof slab M20 Design Concrete,Twoway slab how
many days wait for remooving of shuttering?
Answer Posted / vipin sharma
As per IS 456:2000, the slab shuttering can be removed
after 3 days but immediate after removal of shuttering
proping of the slab need to be done and for beam the
shuttering can be removed after 7 days subject to proping.
Advisable
slab shuttering removal- 7days
Beam bottom less than 6 meter- 14 days
Beam bottom greater than 6 meter- 21days
| Is This Answer Correct ? | 3 Yes | 2 No |
Post New Answer View All Answers
What is bylayer?
How to hide dimensions in autocad?
how to calculate spacing rod in column
what is escalation?how it is done?
std penetration resistance in very stiff clays lies bet 2 & 4 4 & 8 8 & 15 15 & 30
what will be the cost of thickness of 125mmor rcc measurement of 52x33.75 feet
How to test cement,sand,20mmbluemetal,40mmbluemetal,bricks,concrete by visual and instrument
What is M40 _ TOR - EQ and B.F.S
Floor tile measurement? Wall to wall or skirting to skirting
Can anyone tell me the sequence of the activities in a drawing room, kitchen & Toilet including civil work, finishing, electrical & plumbing fittings
1m square 20mm plastering how much of water need curing work
what is high type road and low type roads
Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day
How many feet are in 4 square yards?
could u tell me how to used deform stell bar in reinforce concret?i wanna know the general using in the site!