Answer Posted / rajeeb lochan rout
If PCC is M10 (1:3:6) cost will be about 3500 Rupees per
Cum and RCC of M20 or 25 cost around 4800. Brick cost will
be depend upon brick rate if brick Rs 3 per no. then cost
3200 Rupees per Cum.
| Is This Answer Correct ? | 14 Yes | 10 No |
Post New Answer View All Answers
Gave a cantilever beam with 3 legs.Told to draw the bending moment diagrams, axial force diagrams and shear force diagrams.From BMD he asked to show how the reinforcement will be provided on the tension side.
How to make tiles floor step by step procedure?
What is difference between code and standard and specification?
what post do you prefer to work in this company and why do you think you can serve better in such position?
Explain major differences between routing maintenance and major maintenance.
How many square meter can mason layout chb per hour
significance of specific surface area of particles?
to minimize budget cost of building , what can i do
Does degree of bend of rebars has any effect on strength of the member? For example- if a beam is designed with 45 degree bent up bar with respect to architechtural needs and is not 45 in practical so will there be any reduction in the strength of member?
How foundation is designed, Column design and beam design
Hi.. Can i get hel in finding HPCL previous year question paper? plz help me in finding thiss..
How to calculate unit weight of concrete for m40 grade.
how to calculate steel for slab or footings?
do we consider shrinkage factor for calculating cement consumption for CM mixes for different works?
Why joints are provided?