1 cubic meter contains how many bricks
Answer Posted / m. ranjith kumar
The Standard size of brick is 190*90*90,
Volume of 1 brick=.19*.09*.09=.001539cu.m
No. on bricks per 1cu.m= 1/volume of 1 brick=1/.001539
= 649.77 (650nos)
| Is This Answer Correct ? | 96 Yes | 59 No |
Post New Answer View All Answers
how to convert sand in Cft to Kgs
With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr
What is thumb rule in quantity and cost estimation of a residential building in civil engineering??
Hollow block masonry in cement mortar 1:4, 40×20×20cms in superstructure take 10sqm.I want calculation of brick sand
how many numbers of 4inch bricks and get consumed in 9 inch BB masonary wall in cubic feet.plz send my below e.mail adress
1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.
For the symmetrical continuous beam shown in figure, Prestressed with a force P = 1500 KN along parabolic curve as shown, compute the extreme fiber stresses over the central support for the uniformly distributed load of 24 kn/m. Use load balancing method.
How to calculate woden area in sft and Cft
Define What are the uses of Groynes?
Find out Cutting Length of Steel for Right angle Triangle? Where Opposite Side 4m, Adjacent side 6m. (Assume cover 40mm)
which has high compressive strength between hollow block and brick masonry?
400 ku d/c clearess ketan hota hai?
a sewer which receives the discharge of no. of house sewer is called house sewer lateral sewer intrcepting sewer sub-main sewer
give me the rate analysis for Bituminous Macadam and SDBC
what is SDLC ?and write a 'c'program for to swapping the three numbers?