Answer Posted / niloy
Buckolz Relay is connected between transformer tank and
conservator.It gives protection from mainly over
heating.The overheating can be done by any way-- by
sparking or by short circuit or by any internal fault.When
transformer oil overheated it decomposes itself and create
some hydrocarbon and produce hydrogen gas.. This light
weight hydrogen gas moves to the upward direction and trap
into the buckolz relay.After collecting a sufficient
ammount of gas the buckolz relay give a alarm signal and
trip the breaker to protect the transformer to getting
damaged from over heating.
We can collect the gas stored in the buckolz relay and can
analyse it to know the types of fault.In big transformer a
gas holder is connected to the buckolz relay to collect the
gas..
| Is This Answer Correct ? | 9 Yes | 0 No |
Post New Answer View All Answers
What are the section criteria for cables. Now everywhere XLPE power cable is used or PVC is also used?.
How to calculate no of EARTH PIT? Describe the formula as per IS standard?
hi plz send me reliance placement papers..i.e electrical technical papers that have been asked in reliance test.
what is W.T?specify the acceptable range?
How earthing of switchgear system to be done.
What is the maximum number of swithes that can be connected in series up to down stream point in an LV Distribution system?
sir iam from electrical and electronics branch ,can i appear for the hpcl offline requirtment? if yes please mail me on vikram_raju25@yahoo.co.in
how oil in the MOCB was reduced compared with OCB? what are the features of the MOCB?
how a resistor resists to flow the current?how an inductor oppses the sudden change in current?how a capacitor opposes a DC voltage.
Any Electrical Engineering jobs?Please refer for interviews. Thank you
physical identification of HT & LT panel
why capacitive load is not used in routine life????any reason is there ??????
what could be the RMS value and average value of a 4 phase sine wave?
dear sir/madam i want to get some knowledge about RRB EXAMINATION(section engineer) 1- what is minimum cut off 2- wht portion is major portion . 3- can any body provide Sample paper. thanks & regards ashish
sir please tel me how calucalte kwh if home taken load 30ams how maney kwh taken per day.and 3phase motor 5hp per hars how maney load teken and how mach kwh and forward me to electrical table for calicalte kwh and kvr and kvah