whatis the minimum strength required for M-25 grade
concrete in 14days compressive test? What is the procedure
of calculation?
Answer Posted / prosun roy
A Concrete block when tested for compressive strength must
exibit a minimum of 70% strength by 14 days as per IS.
However it is seen concrete usually gains more than 90% of
its characteristics strength by that period if O.P.C is
used, PPC may delay.
Is This Answer Correct ? | 17 Yes | 2 No |
Post New Answer View All Answers
how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?
What is the effect of a building collapse?
how can we construct building without foundation providing only grade beam at ground level
how calculate the bearing from two coordinates?
Doul Bar reinforcement and details of drawing.
how to control PQI (Project Quality Index)
Define Workability ?
At one time what is the height of Lift for concreting for Bridge Piers Class B Loading and refer the code.
What is meant by autocad?
Can any body help me out by telling hoe swelling pressure test of soil is carried out ? some body told me the procedure & formula (change in length /116.3*100%) but still i am confused ? pls help.
i have a interlock pavement work.i need to compact about 2000 sq metres of sub base grade c of thickness 15 cm.what is the amount of water required for compaction ??
What is the maximum crushing load in Kg & crushing strength in N/mm2 for M25 & M 15 Grade concrete
what happening if we casting HV shunt reactor foundation pad at 50cm height different time (One day difference)
give me the rate analysis for Bituminous Macadam and SDBC
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.