IF THE OUTPUT OF A 100KVA, 415V GENERATOR IS STEPPED UP TO
11KV WITH A 500KVA TRANSFORMER,CAN THE TRANSFORMER BE
LOADED ABOVE THE SOURCE GENERATOR RATING?
Answer Posted / k.prakashchandra
No. Tranformer is for only stepping up the voltage, not the
power which should not be allowed to rise above the
capacity of the generator
| Is This Answer Correct ? | 6 Yes | 0 No |
Post New Answer View All Answers
what will happen if synchronous machine rotor fed from single phase ac supply
How dia computation perfomed in cold rolling mills .
I have c license but I don't know eligibility of Max Kilo Volts under the electrical licensing board.
Why use the vcb at high transmission system ? Why can’t use acb?
how can get electrical "c" licence.i am complited in DEEE.PASSING YEAR OF 1993.WORKING IN PVT COCERN LT LINE.PLEASE ADVISE ME .CELL NO 9994786021
surge tank, hrc fuse, earthing transformer, firm power objective type
what is the difference between transformer,converter and transducer
Write the analogous electrical elements in force voltage analogy for the elements of mechanical translational system.
how to calculate the no load current in transformer?
How earthing/grounding done in aeroplanes and ships.
how to calculate single phase motor efficiency ?
lamination figures
my bachelors was done with EEE now i got admit in NU with CS as course. how to answer this qns 1) why u choose cs? 2) why u changed from eee to cs
What is mean by hot and cold loop testing?
Does the motor power displayed on the Motor name plate is the mechnical power motor delivers or it is consumed power from the system?