what is suspension criteria and exit criterai in test
plan/????
Answer Posted / b.ramyasri
hai....
Suspension/Resumption Criteria in a Software Test Plan :
If any defects are found which seriously impact the test
progress the test lead may choose to supend testing.
The criteria which are considered for suspension or
resumption are :
[a] hardware / software not available at the time indicated
in the project schedule
[b] the build contians many serious defects which seriously
prevent or limit testing progress
[c] Assigned test resources are not available when needed
by the test team
Resumption Criteria :
If testing is suspended, resumption will only occur when
the problem(s) that caused the suspension have been
resolved. When a critical defect is the cause of the
suspension, the “FIX” must be verified by the testing team
before testing is resumed
| Is This Answer Correct ? | 7 Yes | 2 No |
Post New Answer View All Answers
What are the queries mostly asked in testing ? give me some examples.
Explain Testing process in your organization?
what is traceability matrix and its usefulness
how we write test cases to brs,srs,hlds,llds
On login window for username and password auto populated field means what !
What processes/methodologies are you familiar with?
What r all the security problems u r facing & the measures taken to solve.
functional testing test cases for transfer funds ?
I have 2 years of exp. in testing and looking for a change if any body knows, about any vacancy in testing then plz contact me on deepti_ac@yahoo.co.in
Actually by using severity you should know which one you need to solve so what is the need of priority?
What is difference between web site testing, desktop application testing and wireless application testing? what is the difference in testing strategy to test them?
Am putting E-commerce project in my resume can any one please tell me about E-commerce application explaination..
When first time we are testing the screen then we have to write that this screen should contains so & so columns [ suppose there r 10 columns on that screen]in the expected result
date format and we should 8 digits - not accepted only /accepted write how many in test cases in the date format valid , and in valid
how to connect your project in database?