How a project is made and deliverd to client? please put all
detailed steps internally?
Answer Posted / shri
Initiating, planning, executing and controling and closure
of project.
| Is This Answer Correct ? | 4 Yes | 2 No |
Post New Answer View All Answers
Three people are responsible for establishing cost of quality theories. Crosby and Juran are two of them, and their theories respectively are: A. Grades of quality, fitness for use B. Fitness for use, zero defects C. Zero defects, fitness for use D. Cost of quality, zero defects
You are the project manager for a cable service provider. Your team members are amiable with each other and are careful to make project decisions jointly. Which of the following is true? A. They are in the smoothing stage of Team Development. B. They are in the norming stage of Team Development. C. They are in the forming stage of Team Development. D. They are in the forcing stage of Team Development.
What are the qualities of a good project manager?
Which of the following brings together a set of tools and techniques used to describe, organize, and monitor the work of project activities? A. Project managers B. Guide to the PMBOK C. Project management D. Stakeholders
You have just prepared an RFP for release. Your project involves a substantial amount of contract work detailed in the RFP. Your favorite vendor drops by and offers to give you and your spouse the use of their company condo for your upcoming vacation. It's located in a beautiful resort community that happens to be one of your favorite places to go for a get away. What is the most appropriate response? A. Thank the vendor but decline the offer, as you know this could be considered a conflict of interest. B. Thank the vendor and accept. This vendor is always offering you incentives like this, so this offer does not likely have anything to do with the recent RFP release. C. Thank the vendor, accept the offer, and immediately tell your project sponsor so they're aware of what you're doing. D. Thank the vendor but decline the offer because you've already made another arrangement for this vacation. Ask them if you can take a rain check and arrange another time to use the condo.
Your company has asked you to be the project manager for the product introduction of their new DeskTop Rock media system. You recently published the scope statement and the supporting detail. The supporting detail contains all of the following except: A. Constraints B. Other project information not noted in the scope statement C. Code of accounts D. Assumptions
What is the difference between direct and indirect measures?
You are the project manger for Xylophone Phonics. They produce children's software programs that teach basic reading and math skills. You are ready to assign project roles, responsibilities, and reporting relationships. Which project Planning process are you working on? A. Resource Planning B. Organizational Planning C. Staff Acquisition D. Human Resource Acquisition
You do not expect the types of variances that have occurred on the project to date to continue. If BAC = 300, ETC = 275, PV= 300, AC = 200, EV = 250, and CPI = 1.25, what is the EAC? A. 240 B. 250 C. 475 D. 150
You are a project manager for Safari Outfitters. Your company is going to offer a new product line in the upcoming spring catalog. Your project team has 10 months to secure contracts with suppliers, finalize the designs, get the product into the catalog, and stock the warehouse. This is an example of: A. An assumption because the project team has worked on projects like this before and know they can meet the 10-month deadline B. An assumption because the project team has a limited amount of time to complete the project C. A constraint because the project team has a limited amount of time to complete the project D. A constraint because the project team is working with a new product line that hasn't been developed before
The Critical Path Method is a mathematical tool and technique of the Schedule Development process. All of the following are true regarding CPM except: A. Determines a single early and late start date and a single early and late finish date B. Calculates expected value C. Focuses on the calculation of float time D. Shows the critical path, or the path with the longest duration
What are the initiation process outputs? A. Project charter, identification and assignment of project manager, constraints, and project overview documents B. Project charter, project overview, feasibility study, and constraints C. Project charter, identification and assignment of project manager, constraints, and assumptions D. Identification and assignment of project manager, project overview, constraints, and assumptions
What are the triple constraints? A. Time, schedules, and quality B. Time, availability, and quality C. Time, money, and schedules D. Time, money, and quality
Which logical relationship does the PDM use most often? A. Start to finish B. Start to start C. Finish to finish D. Finish to start
You are working on a project to develop a new website for your company. You are monitoring results of the project to determine if they comply with standards set out during the Planning processes. You are also taking steps to eliminate unsatisfactory results. This might mean rework in some cases. Which process are you in? A. Risk Monitoring and Control B. Quality Control C. Integrated Change Control E. Scope Change Control