Answer Posted / mukesh budhauliya
These are three parameters which are required to control in
order to ensure the healthiness of boiler.
1: boiler feed water flow control
2: boiler fuel firing control
3: boiler drum level control
| Is This Answer Correct ? | 2 Yes | 9 No |
Post New Answer View All Answers
selection of the zener barrier for the hazardeous area zone 0
What inherent design and operating principles are included in a modern control system to use predictive maintenance practices to increase overall system reliability?
need to calculate flow rate with the help of dp range and orifice bore dia and size. range is 0 to 400 inwc and orifice size is 12 inch 150 # rf and bore dia is 7.180 inch. need to calculation for flow rate
Give 2 application of quartz crystal used for process parameter measurement.
Sir,I am going to sit for IOCL written test exam. recently.Can anyone tell me the name of 'Objective type Question Book on Instrumentation Engineering ' which will help me. Pl. mail to bidyut_71@rediffmail.com / bidyut.saha2008@indiatimes.com / bidyut.saha09@yahoo.in
What is the PLC configuration in Cement industry?
1. For Steam drum level signal, why do we compensate with drum pressure signal? 2.For main steam Flow signal is comensated with main steam temperature signal and main steam pressure signal why?
PT RTD Range: -200 to 500 degree celsius If I configured in DCS Lower range and Upper range . In face plate it shows red colour due to overa range how was the characteristics look If the temperature is more than operating range. how was the characteristics look . whether its in Resistance vs Temperature curve is Linear or Non linear
what about your moleg in pogrees with company
How to calibrate capillary type level transmitter
I need to know steps to Calibration Valve Guard......
what are procedure of sox-nox calibration
The Design Calculation of Level Transmitter For Different Structure open & Closed Vessel, Eg. Diff. Level Tx., Capacitance For Continous Operation
where uses EXe /EXd/Exo/Exn/Exp/Exq/EXia
Hi, I am Newely Joined in Construction company instrument engineer? Any one can Plz tell me How can I advanced preparation for Releated Engineering and construction Documents?