What is the quantity of cement, sand, and gravel to be used
in M20 grade of concrete for 1000 x 1000 x 1000 mm of sand
(for cement please mention in kilos, and for sand and
gravel please mention it in CFT)
Answer Posted / reethesh.m.p.
1000mmx1000mmx1000mm =1 mx1mx1m = 1cum ok
M20 Grade =1:1.5:3
summation of proportion=1+1.5+3=5.5
1.54cum of dry materials of concrete will yield only 1 cum
concrete after adding water.So the constant is 1.54
Quantity of cement for 1m3=1 x1/5.5x1.54 = 0.28 cum
1m3 cement=1440kg. So cement for 1m3=0.28x1440=403.2 kg
sand=easy method=1.5xcement=1.5x0.28=0.42 m3x35.313=14.83cft
or sand=1x1.5/5.5x1.54=0.42 m3x35.313=14.83 cft
Coarse aggregate = 3xcement or 2xsand=(3x0.28) or (2x0.42)
=0.84cum x 35.313 = 29.66 cft
or coarse aggregate= 1x3/5.5x1.54=0.84 m3x35.313=29.66 cft
Is This Answer Correct ? | 16 Yes | 7 No |
Post New Answer View All Answers
Define absolute co-ordinates?
flow of fluid takes place viscosity compressibilityu surface tension deformation under shear force
how to calculate the crushing strength of cement concrete paver blocks 100x100x60 mm thich.
What is the strongest bridge for a school contest?
How to calculate canal slope curvature qty!
Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?
What is type failure of road surface? how to repair the failure of road surface?
What expenses counted in contingencies and how much it is in related to built-up area of the building.
five benefits of using standard terminology in the measurement process
why the profile of shell of natural draught cooling tower is hyperabolic.
CAN V USE CRUSH SAND FOR CLAY BRICK MASONARY
what is the use of steel rods of 16mm or 20mm used for 4.45mts for closing gutter.one mate consumes how many kgs with a gap of 6inches.
we have a bore well 275 depth & water is deliver at distance of 1000 feet from the borewell here iam not include the distance of depth and the deliver water horizontally at our reserviour tank on ground level
How will be cutting in timber plate size 600*400 column size
In foundation design, while we do the base pressure check, we normally check if the attained pressure value is less than the GROSS BEARING CAPACITY of the soil which is the sum of net bearing capacity of soil and the overburden pressure. Actually, the overburden pressure acts against the net bearing capacity of the soil and I feel that we are actually increasing the bearing capacity value and doing the check. I feel that this is NOT right. Please clarify on this.