WHAT IS THE %WASTAGES OF CEMENT, BRICK,TILES, STEEL,IN 1
M3,10M2,1 TON RESPECTIVELY
Answer Posted / dushyant bansal
The Permissible wastage for cement is 3%, for bricks it is
2.5 % and for tiles it depends on the floor shape and size
which can be permitted upto 6%, while wastage is steel is
allowed only 2.5%
| Is This Answer Correct ? | 13 Yes | 9 No |
Post New Answer View All Answers
WHAT IS YOUR CURRENT SALARY
what will be density of a cement bag if its weight and volume are 50kg and 1.25 cft respectively???????
how many mason and labaur work for a 1 brass bricks plz let me know the calculate & how to made calculation for this and whats the formulas for this?
do we decide reinforcement steel , based on bending moment ? give example with continous slab?
what is the ingredient value of 40mm and 20mm aggregates?
how do we design mix ratio?
1. What is coefficient use for calculation of shuttering. 2. What is coefficient use for calculation of reinforcement in one cum of concrete.
How u can calculate the Octagon ring distance from center of raft in 275 mtr chimney slipform errection? cantact no:0993455097
what course did you consider thinking before you enrolled in college?
what is the difference between np2 and np3 concrete mix
Define What is the meaning of a blue land surveyors flag?
Did any of the egyptian pyramids ever fall down?
what is the use of water bar in water tank and is this an extra item in estimate?
What are the different types of civil engineering?
why are you joining in this (applied post) job and your aim for this job