Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

What is Business Blue Print Phase? Have you worked on this
topic with your client?Have you conducted workshops on
Business Blue Print? In Workshops what they will do in BBP
stage? Explain in detail with reference to your client? I
have been asked this question in an recent interview?
Please give answer with reference to your Project/ Client
along with detailed explanation & examples? Please give
answers asap....Waiting for your reply eagerly...
Thanks in Advance.

Answer Posted / rajiv trivedi

Basically the following will be the roles &
responsibilities of an SD consultant: 1. Creating the
business blue print (BBP). The business blue print contains
2 parts - ASIS = This part contains the explanation of the
current organizational structure, master data & processes,
the *requirements* are mentioned below in the ASIS section.
TOBE = This part contains the information as to how the
organizational structure, master data & processes would be
mapped in SAP. The solution for the requirements mentioned
will be clearly specified in the TOBE section. GAPS if any
will be mentioned in the TOBE section, GAP is the bridge
between the ASIS & TOBE, like if requirement can be mapped
in standard SAP, then GAP will be "A" and if requirement
iss to be fulfilled through some development , then GAP
will be "C". To discuss about the ASIS part, you have to be
thorough with the sales domain & ask the key users relevant
questions so as to capture all the processes & masters. You
have to give them a presentation of what SAP SD is all
about so that at the time of actual discussion they have
some idea about the offerings in SAP. The ASIS part is
discussed with the key users & the TOBE part is prepared
purely by the functional consultant. The BBP has to be in
detail so that everyone in the project always has an idea
as to what will the system look like after configuration.
The BBP is signed off by the stakeholders involved in the
project & after this the configuration will start. 2.
Realization - As an SD consultant you have to configure the
system as per the BBP, then provide the Functional
specifications to the ABAP developers for development of
reports & layouts. 3. Testing - UAT & integration testing
with the client. You have to issue the templates for the
master data & open items data. Master data - Customer
master, finished goods material master, pricing master,
customer material information record, customer credit
limit. Open items - open sales orders, open contracts. Get
the sign off on all UATS & integration testing. 4. If any
fine tuning is required after testing this will be done in
the Final Preparation phase. In case you come across any
new requirements which was not mentioned in the BBP, then
such new requirements have to be addressed through the
*Change Request Form*. The change request forms requires
the approval from the steering committee members. Provide
the request numbers in proper sequence to the Basis
consultant so that the configuration can be moved in PRD
server. Upload the master data & open items data in the PRD
server through LSMW or BDC. 5. Go-Live = Running an entire
sales cycle = sales order - delivery - invoice (accounting
document has to be generated) will be go-live. Also the
invoice print out has to be generated through SAP. Note: 1.
Whatever meetings & discussions are there with the key
users should be properly documented. These were some of the
rles & responsibilities of an SD consultant

Is This Answer Correct ?    14 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to disable the 'import all' button on stms for the queues in sap? : transportation management

1425


What is ‘consignment stock processes'?

1146


What is a sales organization, distribution channel, division?

1281


Can anyone please tell me what's above the pricing procedure, what are the field that determined specific pricing procure so pricing determination?

1206


TELL ME FIVE REPORTS, VA05 TELL THE FIELD SELECTIONS

2286


Hi SD Gurus, What is the difference between the Consignment Fill up (CF) & Consignment Pick up (CP) with relation to Sales Document Types, item Categories & Schedule line Categories? Also give definition of both Consignment Fill Up & Consignment Pick Up along with detailed explanation in relation to its configuration& customization steps along with Business Scenarios? Explain in detail about how do you copy an existing Sales Document type CF & CP, how do you name it ( Plz give Name key from your real time data)and what are the customizations you have done for your client? Do provide the document flow for both the Document Types CF & CP? Please provide as many real time data examples as many as possible with reference to your client/ Project? I have interview within 1-2 days? So, I request you to provide solutions to above question as early as possible? Your timely help would be greatly appreciated? Thanks in advance Regards

3703


Can you 'block' a transaction for a material that is 'flagged for deletion'?

1143


What is the use of customer account group?

1259


Once you create a sales order, how do you confirm to the customer like I have the stock for ATP to check for the customer?

793


Where in the sale order would you enter the serial numbers for material?

1152


Explain the assignments among organizational units in sd

1245


Describe the process flow for a credit memo.

1058


There is an interface between sd and fi in invoicing. Can you think of another interface between sd and fi?

1159


Where is the logic that controls this and how do we change it?

1164


Explain the term "as is" ?

1105