Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to calculate transformer capacity requirement for a
project site?

Answer Posted / mahesh sali

THE CAPACITY OF TRANSFORMER USED FOR SITE APPLICATION SHALL
BE CALCULATED BY FOLLOWING CONSIDERATION;

CAL.TOTAL CONNECTED LOAD
BASE ON KW & ASSUMATION OF 0.8 P.F.
CAL. THE KVA/ MVA RATING OF X'MER I.E. KW/0.8
AFTER GETTING KVA/MVA ADD THE 20% IN CAL.KAV/MVA

I.E. KVA/MVA + 0.2*KVA/MVA

20% EXTRA AS PER IEEE RULE

AS PER IEEE NORM ,UR TRANSFORMER SHOULD BE LOADED AT 80% OF
UR FULL CAPACITY OF UR TRANSFOMER.

I HOPE ABOVE INF. IS SUFFICIENT.

THANKING U

Is This Answer Correct ?    26 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Is there a possibility to use such a treshold voltage for the NMOS part of a CMOS circuit that during the switching it will start conducting only after the PMOS part will be already closed, by this eliminating the leakedge current? Please note, I'm not asking about the well bias in standby mode, but about the "antileakedge" measures during normal operation.

2029


what is the reactance,capacitance & impedence electrical armoured & unarmored Cables.

2147


What is vaccum currcuit breaker.define with cause and where be use it device?

1078


how do i commission a distribution transformer knowing all its ratings and transformation ratios?d

4530


Did RMU have ct and pt ?

1328


Difference between RCCB, RCBO and ELMCB.

4042


how did i get the competency certificate as electricle supervisor. iam completed my b.tech.but i dnt have any experince, this certificate is required for applyng ongc mangement trainees. what should i do sir please suggested me

1863


DESCRIBE THE CONSTRUCTION ANDOPERATION OF BELT CONVEYORS AND SCR CONVEYORS , DRAW NEAT SKETCHES

2033


How will A Medium voltage circuit breaker(11 kV voltage level) operate under short circuit fault condition whether It is having short circuit release like Low voltage circuit breaker or relay should be given?

1897


-What shall be short circuit current of LV switchgear for a 1000 kva, 11.415kv, 3 phase tranformer with 5% reactance.

2084


pls tell us AC plant are how do work and parts name with picture

1920


PLZ SEND ME SOME UNIQUE PROJECT OF ELECTRICAL ENG (B.TECH)

1924


importance of reactive power management

1999


what is the purpose of high speed earth switch in gas insulated substat

2951


Define average demand?

1311