11 kv metering is done in my factory.Meter show PF 1.000
but kvarh lag&lead show 24&94 respectively & Avg.PF
is .956 .? is what i do for inproove my PF to 1.000
Answer Posted / vinit patil
Your Meter reads Power factor at load center. In your case
load center might be far away from your tariff meter. Since
your APFC meter shows PF 1.00 but at your tariff meter on
11 KV side p.f still lagging. This happens because of
transformer inductance. Add 10 % KVAR of transformer
capacity directly in ON position. Your problem will go out.
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
How would you calculate power loss in a resistor?
On what basis do you decide the ONAN (Oil Natural air natural) or Dry type transformer for a project?
Which device of PlC does share load between DG sets when DG are running in perallel?
what type of motor used to move a 1 ton gate? and relate ratings with load.
how can get electrical "c" licence.i am complited in DEEE.PASSING YEAR OF 1993.WORKING IN PVT COCERN LT LINE.PLEASE ADVISE ME .CELL NO 9994786021
What will happen if we introduce negative feedback to a control system that uses a positive feedback?
i karmveer bharti persuing b.tech . plz send me syllabus and name of reference books. for preparation of section eng.
Please tell me in DETAIL about the following 3 types of fuses or recommend me a good power system protection book or a website link ? 1.Dropout Fuse 2.Striker Fuse 3.Empulsive fuse (not sure if its impulsive or explosion fuse , sorry)
How can we checked Killo Watts of Motor & Alternator?
why does the magnetic balance tests at transformer?
what is the formula of starting current of 3phase and 1 phase motor???
why we can use 1 to 5V dc
acb(AIR CIRCUIT BREAKER)NOT CHARGING AUTO
to hook up ten 50 amp rv pedastels at a lenth of 600 feet from the service what size will my service need to be and the size of wire will I have to run to each pedastel in series??????
for what voltage will reactive power be largest in 380 kv line : a) 375kv b)380kv c)385kv