11 kv metering is done in my factory.Meter show PF 1.000
but kvarh lag&lead show 24&94 respectively & Avg.PF
is .956 .? is what i do for inproove my PF to 1.000
Answer Posted / vinit patil
Your Meter reads Power factor at load center. In your case
load center might be far away from your tariff meter. Since
your APFC meter shows PF 1.00 but at your tariff meter on
11 KV side p.f still lagging. This happens because of
transformer inductance. Add 10 % KVAR of transformer
capacity directly in ON position. Your problem will go out.
Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
how make megger test for control cable like 12c x 1.5mm and what it apply voltage and test timing details.
how ceiling fan worked?
How to calculate fault level of 11 KV system
Q) Write VBscript code along with QTPscript code in QTP tool for below scenario 1. Launch yahoo site(i know) 2. Do loogin(i know) 3.Click inbox link(i know) 4.Go to every page of mail box and count no.of read mails and no.of unread mails(i know) 5.Store page numbers, read mail count and unread mail count in a new excel file sheet 6.Create 10 types of graphs on that data 7.Do logout and close site(i know) 8.Save new excel files with graph
How to decide DO set rating of Transformer?
how to compute kAIC? with formulas...
How do you determine the size of transformer radiators in a transformer?
how can we save enegry by using VFD for Resiprocating Air compressor which is having more unloading running hours
The shot circuit in any winding of transformer result? Explain
what is the carona effects meaning in HT line transmmission system
how to deside the capacity of chock for drive?
How Can I calculate for the photometrics requirements for a street lighting? Data given are: 45 units of 6 meter light pole with 150 watts metal halide lamp, 220 volts and installed in a promenade area.
What is a advantage of Self Reset Lockout ? On Fault breaker get trip & fault no longer exist then self reset lockout how inform us?
Why transformer used in UPS??
I have 2500KVA transformer delta/star,13.8KV/380V provided with LV 4000A breaker. Already I have 2300KW motor feeder with a full load 90%. Is it possible to connect another 1600A from that breaker? If so how the calculation is done?