Basicaly Transformers having two type of tests 1-
Manufacturing & 2- Field test, Manufacturing test are
described Above & Field tests are carried out during the
Commissioning at site.Field tests are given belwo..

Insulation Resistance Test- Phase to Phase, Phase to Earth,
Winding Resistacne Test.
Testing & setting of WTI & OTI.
Vector Group Testing.
Magnetinc Ballance Test
Ratio Test.
Knee Point Test.
Tan Delta Test ( This is Also IR test)
Hi Voltage Impulse Test (if Client requested)
etc...

Is This Answer Correct ?    3 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is a single phase autotransformer?

643


what are the pecularity of shaver sockets ?

1466


why the frequency and voltage in india is 230v and 50HZ. when compared to USA say 110v and 60 HZ.

1011


In our factory so many iron pillors are exists for supporting the shed/Hangar. If do more no of earthings at one piller instead of doing more earth pits in many locations and running earth strip around the hanger, I can save the money. Please suggest this method is acceptable as per Is specifications though the Earth resitance of the farthest piller is with in the limits as per IS specifications.

1649


how to calculate regulation constants for over head lines? and what are the regulation constant for raccoon conductor at different voltage level and different P.F?

1465






how to define tell me about self

1519


Is there any guideline say about display of earthing value near to earth pit

708


i am completed my degree(B.E EEE) 2014 anychance to get electrical licence plz help me

1671


DG Earth Value?

1865


what is a pilot wiring and whys that called a pilot wiers

1354


how to get electrical supervisor competency certificate in gujarat. i did 3 year diploma in electrical

2075


What is load boxes ?

1597


What are the raitings of Mcb,mccb and Acb in detail ??

1104


what is the profesional board for electrical engineer what is thepast and during construction for electrical engineering

1466


How to operate a ac chilar plant?

1960