in our sub station why we step down firstly 33kv\11kv then
11kv to 430v. can we direct step down 33v to 430.v.
Answer Posted / vrs rathore
Yes we can, but if our exixting system is workable for only
11kv and required capacity is more then 4000kva then we
have to take 33kv connection and after that it has to step
down 11kv for supplying our esisting system, which is
working only for 11kv/430v.
Is This Answer Correct ? | 3 Yes | 2 No |
Post New Answer View All Answers
what is the principle of operation of CFL ??
1. transformer design formula ? 2. how to calculate the primary turns and secondry turns ? 3. core types ? 4. how to find the primary current and secondry current ? 5. how to calculate the stacking factor ? 6. range of fulx density ?
What is the method for testing the differential protection stabilty in generator? When the time of starting What will happen if differentail protection connection wrong means?
What facility we get after CT secondary earthing and how?
What is the maximum operating temperature for a thermoplastic insulated cable?
What was your role in the silicon evaluation/product ramp? What tools did you use?
give single line diagram of D.G distribution form alternator to main L.T panel?
How to calculate the electrical load for a standard telecom BTS shelter and choose the DG set capacity for the same load?
for a 500 KVA connected load, I calculated 30% of capactor for power correction. Even after using 225 KVR capactor PF is not improving. What could be reason for low Phase correction factor?
define displacement & magnitude ?
in dc series motor if field wdg is shorted then
1. what is usage for power factor in industries?? 2.why we need to monitor power factor??
What is the main purpose of c.f.b.c.boiler
where are the circulat the diesel in DG parts name with pictue
in my working site. momentary jerck in electrical supply ocurred frequently which cause of multiple losses in our electrical equipements. how can we protect our electrical machines and equipements in this situation.