why loss of strength in concrete in 7 days cube test i am
not geting mim 7 days strength that is 67 percent for M-35
and my mix design is perfect there is no doughty,and my
results are near to 7days percentage but not 67 percent.
Answer Posted / v.purushotham
The fallowing check points to be done:
 In between interval you should check the mix ratio
i.e. volume/ weight of material,
 Check cement ratio,
 Check slump while pouring the concrete,
 Check the proper mixing of concrete,
 Check the procedure of filling and compacting of
cube mould,
 Check the bulkage of sand,
 Check the gradation of material every 15/ 30 days
interval and compare the designed materials properties,
 Last but not least check the proper curing of
concrete cubes.
| Is This Answer Correct ? | 6 Yes | 0 No |
Post New Answer View All Answers
What is the minimum size of the particles of silt soil?
How do you compute moisture correction using the parameters gathered from Nuclear Density Gauge Apparatus and the moisture contents results from the lab.?
how to calculate total cost for slab 35'×8'
give me the rate analysis for Bituminous Macadam and SDBC
howto calculate the quantities of material used in fly ash brick after finding the volume??
Sometimes the side of concrete bridges is observed to turn black in color. What is the reason for this phenomenon?
in the earthquqke the profile of water on dam is parabolic or not
Ratio for 4500 psi concrete
How to find permissible diagonal tensile stress in reinforced brick work
do we decide reinforcement steel , based on bending moment ? give example with continous slab?
Define aligned dimension?
What are the uses of layer?
for Precast foundation howmany days required we can shift the foundation with american Standards i need reference with section any body can help
How to calculate woden area in sft and Cft
how much of quantity of material required for execution of one cubic meter of random rubble masonry in 1:3 cement mortar