HOW TO CALCULATE LABOUR COST FOR CONCRETE WORK PER CUBIC
METER.
Answer Posted / geethu
can u explain ? Head mason - .05 x Rs 200 = Rs 10.00
Mason - .3 x Rs 190 = Rs 57.00
Labour - 2.5 x Rs 90 = Rs 225 ? wht"s mean by 0.05?
| Is This Answer Correct ? | 24 Yes | 18 No |
Post New Answer View All Answers
LET ME KNOW HOW IS CALCULATE RUBBLE WALL .3'00" IN BOTTOM 1' 6" IN TOP HEIGHT 8' 0" AVERAGE. length 200'00". please give correct answer.
What Are The Different Type Of Slump Test Indications?
1) write Short notes about Shellow & Deep well? 2) What is the full form of SPT & SMB? write short notes. 3) write short notes about efficiency of Riveted joint.
what is cross hair cursor?
Explain why concrete barriers have curved surface profiles?
What is the worlds largest concrete dam?
In which code the the maximum height of concrete casting has been explained
What do you mean by the word 'shear'?
What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.
1) What is meant by C-soil in geotechnical Engineering? 2) What is Eve board? 3) What will happen when heat is applied to cement? 4) what do you understand by the lateral dimention ?
Explain the different types of building contracts?
How do you calculate the unit weight of concrete?
VAT and CST ? Which benefits for buyer ? Why benefits?
what is floating slab foundation?
what's the formula for calculate pcc for matt(45mm aggregate)?