What are the skills required to be a project manager?
Followup question, Rate yourself in each of the skill with
examples.

Answer Posted / n krishnaswamy

Project Manager should be well versed in all 9 Knowledge
Areas and Five Process Groups. In Short, Success of Project
Manager depends on 1)Communication Skills 2)Interpersonal
relationship Skills. Project Manager 90% od his time in
commmunication.

Is This Answer Correct ?    7 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are the different project scheduling techniques?

696


Which logical relationship does the PDM use most often? A. Start to finish B. Start to start C. Finish to finish D. Finish to start

1143


All of the following are tools and techniques of the Performance Reporting process except: A. Variance analysis B. Performance reporting C. Information distribution D. Performance reviews

951


During contract negotiations, your vendor tells you that the equipment originally bid in the RFP is no longer available. They say the best solution is to buy the new equipment they're offering, which is a higher price than the original equipment. You have concerns that the new equipment might not be compatible with existing equipment and try to discuss this with them. They remind you that this decision was already made during the last contract negotiation meeting so there's no need to continue to discuss it. This is an example of which of the following? A. Proposal B. Compromise C. Storming D. Fair accomplish

804


What are the qualities of a good project manager?

692






The lowest level of the WBS is called what? A. Code of accounts B. Requirement C. Milestone D. Work package

800


You know that PV = 475, AC = 430, EV = 480, EAC = 40, and BAC = 525. What is VAC? A. 440 B. 390 C. 485 D. 435

1641


Which of the following might require rebaselining of the cost baseline? A. Corrective action B. Revised cost estimates C. Updates to the cost management plan D. Budget updates

790


You are going to take some performance measurements for your current project. You know that PV = 450, AC = 500, and EV = 375. What is the CV and SV respectively? A. CV = 125, and SV = 75 B. CV=-75, and SV=-125 C. CV = 75, and SV = 125 D. CV=-125, and SV=-75

912


Which of the following is true regarding constraints and assumptions? A. Constraints restrict the actions of the project team, and assumptions are considered true for planning purposes. B. Constraints are considered true for planning purposes, and assumptions limit the options of the project team. C. Constraints consider vendor availability and resource availability to be true for planning purposes. Assumptions limit the project teamwork within predefined budgets or time lines. D. Constraints and assumptions are inputs to the Initiation process. They should be documented, as they will be used throughout the project Planning process.

968


You are a project manager for a software manufacturing firm. The project you've just finished created a new software product that is expected to become a number-one seller. A friend of yours is a certified software instructor. They have asked you for a copy of the software prior to the beta release through the marketing department so they can get familiar with it. What is the most appropriate response? A. Since your friend is certified to teach your company's brand of software, provide them with a copy of the software. B. Ask them to sign a nondisclosure agreement before releasing a copy of the software. C. Decline the request since you stand to gain from this transaction by receiving free training. D. Decline the request because the software is the intellectual property of the company.

842


This measurement is the value of the work that's been completed to date: A. PV B. AC C. EV D. EAC

810


You have been asked to submit a proposal for a project that has been put out for bid. Prior to submitting the proposal, your company must register so that their firm is on the qualified seller list. Which of the following is true? A. The qualified seller list provides information about the sellers and is a tool and technique of the Solicitation process. B. The qualified seller list provides information about the project and the company that wrote the RFP and is an input to the Solicitation process. C. The qualified seller list provides information about the project and the company that wrote the RFP and is a tool and technique of the Source Selection process. D. The qualified seller list provides information about the sellers and is an input to the Solicitation process.

687


You need to convey some very complex, detailed information to the project stakeholders. The best method of communicating this kind of information is? A. Verbal B. Vertical C. Horizontal D. Written

712


You are the project manager for an upcoming outdoor concert event. You're working on the procurement plan for the computer software program that will control the lighting and screen projections during the concert. You're comparing the cost of purchasing a software product to the cost of your company programmers writing a custom software program. You are engaged in which of the following? A. Procurement planning B. Sensitivity analysis C. Transference of risk D. Make or buy analysis

982