Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

WHAT IS THE USAGE OF Buckoltz relay IN POWER TRANSFORMER AND
AND HOW ITS FUNCTIONS?

Answer Posted / anant shetye

In power Transformer Gases form so before putting
Transformer in service we have to release that gases & LET
OIL SHOULD come to conservater tank for safe operation ,if
it is not do so and if you give supply to the transformer
Buckoltz relay gets trip & it provide safety to Transformer.

Is This Answer Correct ?    2 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to calculate the time setting for star connection in star delta starter? For example 10KW 3PH Induction motor.

2619


What is the difference between Delta & Wye windings?

2090


What is the basic principal, by which DC voltage level is increased more than the supplied AC voltage during conversion. As upto AC level it is contorrled by firing anlge but after maximum level how is it possible.Please clear picture. OR we have to supply the higher level AC?

1957


Draw a SLD for main panel for school having connected load of 1200kw and emergency generator 200kw.also show the increase of additional load of chiller 225kw in the lv panel indicating meter postion size of transformer ,cables and capacitor bank.

965


how to set relay setting? and example calculation...

2033


hai...... tis is Hemanth. jst now completed electrical engineering... i wanna to apper for ap tranco exam... plzz send me the previous q's paper link......thanx in advance.

2090


please send me jindal previous aptitude and technical question and answer.my email id is deep_raj@live.com

1970


List of equipments required foe industrial repair lab.

1888


block diagram of 2 ups system connected in hot stand by mode?

8052


What is the meaning of HT Trivector Meter ?

2450


PLEASE TELL ME ABOUT QUESTION PAPER OF UPCL ENTERENCE EXAM.

7950


How RTCC panel is working and give single line diagram for RTCC with transformer?

3091


why asa method ZPF method is more accurate than ASA method?

5806


difference between main metering kiosk and check metering kiosk

2991


what will happen if earth of 33 kv cable (earthed system) is not connected to earthing pit?

2025