Cube tests of concrete are failed at 7 days and 28
days.What is your next action?

Answer Posted / nravindran

Go for NDTest, if it is not satisfied go for Core test that
is also failed go for concrete strengthing process As per
structural consultant comments

Is This Answer Correct ?    19 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

a) we have 30nos., 300mm dia, 4m length double under reamed piles.calculate excavation quantity.b) tell concrete qty. also.

12703


insted of bentonite we can use any alternate material in piling ?

1712


Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day

1593


what is smart building materials?

1591


How do you calculate load bearing capacity of a waffle slab?

2220






HOw much % of premium on DSR-2013 currently

1546


what is the 0 value in quantity surveying

1932


how many type of admixtures for water stored structure?

1719


Curing time for 1)R.C.C slab 2)B.W 3)Plastering

1646


"Gates of the dams are generally designed of curved shape". Why?

1605


what is escalation?how it is done?

2106


Different sizes of Hollow blocks and its weight. Thanks.

1929


Why are steel plates inserted inside bearings in elastomeric bearing?

840


Formula of mid span bar

1469


what is work of planning deptt. in any construction compny (in road project)

1889