How many bricks in one cubic meter?
Birck size 22.9*11.4*7.6 joint 12mm
Give me answer with calculations
Answer Posted / thenraj
size of bricks with joint = 0.241*0.126*0.088,Number
of bricks =1 /(size of bricks with joint) = 1 /
(.241x0.126x0.088) = 1/ (0.002672208) =374.22 / cum we
take 375 number of bricks / cum
| Is This Answer Correct ? | 48 Yes | 25 No |
Post New Answer View All Answers
how to calculate quantity of cement,sand & aggregate for u.c.r / r.r masonry in cm 1:6
what is the water cement ratio for plastering
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
What is rate for brick masonry work of 1.0 m3 in cm 1:6?
Explain how you can turn off the display for dimension in CAD?
we have a crushing plant and our product is experiencing flakiness and elongation over limit for granite. what is the solution to this problem? how can it be avoided and what to do differently? It is not ok for batching plants
The 4 main factors to start a construction project are––
hai, kindly send anyone for output workers format details for construction project in foundation to finishing.
what is meant by csr in foundation? what is sbc?what is meant by contour line?
what is the formula to find the diagonal shape stirrups?
Who built the sears tower?
what is meaning of inverted beam.is it way to provide double mat in slab one at bottom and another at topif we go for provision of inverted beam. shall we construct structure with out plinth beam for us we have to construct small bus shelter
Define absolute co-ordinates?
rate analysis hiring of generator 62.5 KVA
how do i remedy a foundatiom that the column bases was cast and aftet 28days crushing the conprehensive strength of the concrete fall below the specification 25N/mm2