How to find quantity of cement mortar?
I want to know the req quantity of cement for plastering 300
sft in final coat with 12 mm. Any math involved? Plz help
Answer Posted / amio
Let's assume
1bag of 50kg cement occupies 0.035cum.
1bag of 50kg cement occupies 0.035cum.
my basis of mortar mix is 1:5
so there are a total of 6bags (1+5)
in 1cum of cement mortar, no of 50kg bags will be
= 1/.035
=28.57 bags of 50kg each
so cement quantity will be (28.57/6)*1=4.76 bags(say 05bags
50kg each)
and sand quantity will be (28.57/6)*5=23.81 bags (say
24bags, 50kg each)
hope this will work
| Is This Answer Correct ? | 1 Yes | 17 No |
Post New Answer View All Answers
What is the use of offset command?
Is it possible to make a feature using an overdefined sketch?
What is structural frames or systems?
What is bmc stands for in bmc software?
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
HOE TO YOU PLAN TO ACCHIEVE THE GOALS?
sir tell me the formula for calculating the volume of 380mm dia double under reamed pile of 4.0 mts depth.
Why reinforcement done in shorter span in two way slabs
suppose that 156000 sq.ft rcc work builtup are.how many % of brick work to rcc work.
what is the max. area can we apply the plate load test ?
I need Bhel engineertrainy test papers in civil engineering please send to email id - hisandy66@gmail.com
How to estimate the shuttering material requirement for a slab and beam and shear wall..? Please send thumbrule to estimate material required ( Plywood, Ms plates, runners, acrospans, jacks)
whaat is blister in box girder bridge and what is its function..
in a building why we are using T beams? why can i adopt beam bottom & Top level as same as slab bottom & Top level?
Can anyone tell me the sequence of the activities in a drawing room, kitchen & Toilet including civil work, finishing, electrical & plumbing fittings