I have one DP transmitter of range 0-500mmWC i have to
calculate its range in M3/hr for flow measurement so whats
the formula.
Answer Posted / kannan.r
range of dp tx and range of output is entirely different.
first of all to measure flow, we need primary elements like
ventury tube, flow nozzle, annubar which will restrict the
flow and so that dp will create.
from the manufacture of the primary element itself the
constant value should be noted. then only we can calculate
the flow using dp tx.
| Is This Answer Correct ? | 6 Yes | 4 No |
Post New Answer View All Answers
Name different parts of a pressure gauge. Explain the use of hair spring in the pressure gauge.
Explain the difference between plc and cnc?
which type of signal used in instrument?
what is instrument philosophy
How to calibrate the flow transmitter
i have done DAE in Instrumentation and Process Control. i have applied for an apprentice training in chemical company after three day my interview will be conduct but i need more information about industrial process control and controller. my e mail is imran_dilsetu@yahoo.com please tell me interview question relative to instrumentation ?
HI, can anybody give details about GAS TREATMENT PLANT CONSTRUCTION,as INSTRUMENTATION ENGINEER what are the responsibilites.what are the instruments mainly instrumentation engineer will deal with
which type of filter gives the constant phase characteristics?
how is work pressure switch& level switch?what is the principle of this?
what is piezoelectric transducer?give an example in power plant n state its principle?
What are primary elements of measuring pressure?
principle of dead weight tester ?
Im having problems with interfase betwen SPI v7.0 and SPPID v5.05. Previous versions of Intools shoul be fixed with SPPIDproj.ocx file. It was necessary to replace this file with one that allows the connection between different versions of SPPID. It is necessary in the current version to do the same?Thanks
how to design orifice plate?what is the equation?
What inherent design and operating principles are included in a modern control system to use predictive maintenance practices to increase overall system reliability?