Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...



What is the quantity of cement, sand, and gravel to be used
in M20 grade of concrete for 1000 x 1000 x 1000 mm of sand
(for cement please mention in kilos, and for sand and
gravel please mention it in CFT)

Answer Posted / rajendra

1000mmx1000mmx1000mm =1 mx1mx1m = 1cum ok
M20 Grade =1:11/2:3
summation of proportion=1+1.5+3=5.5
1.54cum of dry materials of concrete will yield only 1 cum
concrete after adding water.
1cum x1.54/5.5= 0.28 cum
so cement=0.28cum= 0.28/.0347=8.07 bags=403.5 kg
sand=0.42cum= 14.82 cft
aggregate=0.84cum= 29.65 cft

Is This Answer Correct ?    26 Yes 8 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Define polar co ordinates.

1174


How you read 5x3x1 #4 @ 20" 0/C in steel structure?

1475


Coverage of 25mm.thick ratio of 1:4 cement mortar?

1858


Which is stronger solid steel rod or hollow steel pipe?

1359


I have a slab of 20cm thickness of 20m by 4m in wich we are installing 15 tons electric panels , and we have put 4 H-shaped columns under the slab but we have done many cores in the slab which seems very normal , can you help me by telling me how to calculate the bearing capacity of the slab or give me an idea if i should increase more columns Note: load distribution area 12*1.5 m2

2263


With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr

2397


Define angular dimension?

1143


What are the advantages of cad software?

1076


how i convert mm into standard wire guage (SWG)no.

3010


Describe the various methods of concrete curing?

1102


pls give me some basic informations in construction of a structure?

2001


In case if concrete box girder bridges how is the number of cells determined?

1131


afe or not

2127


What is meaning of FREE STANDING STAIRCASE ?

2961


How to calculate steel for beam slab and column

1785