what is the logical concrete mix design for M 30 Grade and the
cement consumption per M3
Answer Posted / navin baranwal
Grade of M30 concrete in 1:1:2 and the cement consumption
is 368 kg/cum.
| Is This Answer Correct ? | 8 Yes | 5 No |
Post New Answer View All Answers
While doing civil foundation of machinery. How will you process for it? & We also fixing plates at top surface of foundation, then what is the procedure?
why we are using stub column..? is it possible to construct steel stub column..?
How much does the leaning tower of pisa lean?
Does brick grows bigger every year?
Calculation of Pier Cap with tapper area?
factory shed foundation l=4, b=3' d=8' rcc foudation for top to bottom pl tell me cement ,steel ,sand ,labour cost ,excavtion,soil is weak not so hard
Why are separation membranes used between concrete pavement slab and sub-base?
What Are The Steps Involved In The Concreting Process, Explain?
For submitting the project loan for bank Residential bldg,Suppose we take Provinding RCC mix 1:2:4 for footings No of footings,length ,Breadth,Height ,qty in cum, at last unit/Rate(Rs) ,i would like to know how do we get the unit/Rate
please what are the required bars for a beams of 6mx6m and 450x300mm, one is continuous and the the second is discontinuous ..Its a commercial building (church)
is there any thumb rule for calculating construction cost of the building with pile foundation per sft. area?
how many shuttering material required for 1000 sq.m built up area.
if mineral admixture add into concrete then what is the differences between full cement concrete & fly ash added concrete of their SP. Gr.?and for the changes of SP. Gr. what is the changes in concrete
what is civil all interview questions
What is the difference between the concrete mix design carried out by IS10262 and by ACI method ?