how do you estimate the # of bags of cement, sand & gravel..
if only given the volume of the project..
Answer Posted / suresh
let the total volume of the concrete is = a
and let the given mix proportion is 1:1.5:3
then the quantity of the
cement required = a*(1.52/(1+1.5+3))m^3 = x m^3
we know that one cubic metre = 1450kg = 29 bags
1 cubic metre = 29 bags
x cubic metre = ?
=(x * 29)/1 bags
now, fine agg = 1.5*x
coarse agg = 3*x
| Is This Answer Correct ? | 36 Yes | 9 No |
Post New Answer View All Answers
what is smart building materials?
How to identify the vitrified tile and ceramic tile by observation only after executing the job.
Prepare a Schedule for a Highrised building from starting stage to Handover?
how much cost of single coat 20mm thick plastering per sqre meter
suppose we have a tendency to make a hole on the surface of the simple supported beam, than where we goes to make it?
What are the basic use of runners and standards of pipelines?
How to fix the reinforcement in footing shorter bar at bottom and longer fix at top.
Civil engineering related
Volume of 25kg putty bag & 40 kg putty bag volume??
What are the ingredients of pre-stressed concrete?
i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?
How to estabilish reinforcement Steel rolling margin for a building projects ?
what is the mix design for M:60 with micro silica andmetakaoline?
GIVE US DETAIL OF YOUR PRESENT EMPLOYMENT STATUS?
What are the different methods for drawing an arc?